Safer maintenance access walkway installed at Frimley Park Hospital

Specialist contractor Pilbeam Construction has installed a lightweight walkway to access a RAAC affected roof at Frimley Park Hospital in Surrey.

Pilbeam worked with Frimley Health NHS Foundation Trust to design, manufacture, and install the new designated load-bearing platform for the £796k project. The contractor also removed and adapted the existing walkway, adjusted building services, and completed a phased installation of new walkway sections across multiple roof zones at the hospital.

Working in partnership with Johnson Design Partnership, Mott MacDonald, and SMP Consulting Engineers – Building Services, Pilbeam used a Fibre Reinforced Polymer (FRP) system to decrease the weight of the new walkway beams, platforms, and handrails to cause the least amount of impact on the existing roof structure.

There was only one access route for the length of the project, but with lighter-weight materials in the FRP system, Pilbeam was able to move items efficiently through a single point of access.

Around 65 per cent of Frimley Park Hospital is affected by RAAC, including areas such as wards, theatres, maternity units, corridors and intensive care. The RAAC planks have significantly exceeded their original 30-year design life.

While plans for a replacement hospital progress, extensive monitoring, maintenance and remedial works continue across the existing site, with the new walkway forming part of the work to maintain safe access to RAAC-affected areas.

Pilbeam Construction MD Alan Corbett said: “This has been a complex but rewarding project which has not only created safer access for maintenance teams, but has helped minimise unnecessary loading on the RAAC-affected roof.

“Our team has vast experience working in healthcare settings and completed this innovative project without causing disruption to healthcare professionals and patients.”

Tanka Ambohang, technical project manager at Frimley Health NHS Foundation Trust, commented: “We were very pleased with the outcome of the work completed by Pilbeam Construction. The new walkway provides safer access for our maintenance teams while helping to minimise unnecessary loading on the existing RAAC roof structure.

“The work was carefully planned and delivered within a busy hospital environment, and I’d like to give special thanks to site manager Bill Musa and his team for their hard work, professionalism and commitment throughout the project.”